Estimate at Completion (EAC) – with Formulae & Examples

Estimate at Completion Title

If you want to forecast the project cost for the completion of the entire project, you will need the indicators “estimate at completion (EAC)” and “to-complete performance index (TCPI)”. Both are part of the data analysis techniques of the control costs process in the PMI’s Project Management Body of Knowledge (PMBOK®, 6 th edition, p. 263-265). They are not only frequently used as indicators in project forecasting but also common for questions in a PMP exam.

This article covers the definition of EAC and the 4 approaches suggested by the PMI, supplemented with the respective formulae and examples. You can also use our EAC calculator to further familiarize yourself with the calculation.

If you intend to calculate indicators that reflect the actual status of your project, read our article on schedule performance index (SPI) and the cost performance index (CPI) and use the free CPI / SPI calculator.